| Stage 1 :- |
 | Upgrade of existing boiler house including strip out of existing 3No calorifiers, 3No boilers and 2No water heaters and installation of 9 No new boilers and associated calorifiers. Re lining of existing gas flue. All to be carried out while maintaining hot and cold water supplies to 118No apartments |
 | Installation of new boosted cold water supply to 118No apartments, inc installation of new cold water tanks and booster sets |
 |
Installation of new heating pipework (buried) to feed existing riser heating pipework |
 | Installation of new secondary heating system pipework to apartments (for future use) |
 | Upgrade of mechanical services into 118No existing apartments including new hot water flow and return and cold water services |
 | Installation of new electrical mains into 118No apartments from remote EDF service heads via a Ryefield distribution board system |
| |
|
| Stage 2 :- |
 | Full mechanical and electrical services in 22 luxury penthouse apartments to be constructed on the roof of existing building |