| The project involved the complete installation of the electrical services for the Imperial College, including extensive integration of campus wide systems for security, CCTV, Fire Alarms and structured cabling systems. The project consisted of refurbishment to part of the Royal School of mines and the creation of 7 new Harvard style lecture theatres and new main feature entrance for the college as new build. |
| |
| These activities summarily consisted of:- |
Installation of LV switchgear and sub-main distribution |
Installation of sub-mains |
Installation of lighting control system |
Installation of earthing and lightning protection |
Installation of emergency lighting |
Installation of fire alarm system |
Installation of security and CCTV systems |
Installation of a structured cabling system |
Specialist interfaces to the audio visual system |