| These activities summarily consisted of:- |
 |
Package Substation with sub-mains cabling to 2 main internal risers |
 |
Essential and Non Essential rising bus-bar systems where provided within two of the risers. Each riser consisted of essential and non essential LV distribution boards at each floor |
 |
Modular wiring installation of the lighting was installed allowing future flexibility for changing Tenant needs |
 |
A fully addressable Fire alarm installation with interfaces for automatic shutdown and controls of lifts, main plant and F.F.L. supply |
 |
Self contained emergency lighting battery packs where installed to meet the M3 requirements |
 |
The basement generator was provided to provide essential coverage to essential circuits and dedicated plant. |
 | Roof Plant:
- Roof Path way lighting and power
- Bulk Electrical Supplies to chiller units and air handling plant |
 |
Externally: - External lighting to colonnade and external facade |